Wednesday, July 01, 2020

MPSC denies Enbridge Energy's request for relief on Line 5 pipeline project, sets Aug. 24 full hearing process for proposal

LANSING -- The Michigan Public Service Commission, on June 30, denied the relief Enbridge Energy LP sought in its request for a declaratory ruling and also rejected the company’s request for ex parte* approval of plans to relocate the Line 5 pipeline to a tunnel beneath the Straits of Mackinac. The Commission established a full hearing process for the proposal.

Enbridge in April filed an application (Case No. U-20763) requesting siting approval under Act 16 of 1929 to replace and relocate the Line 5 section in the Straits of Mackinac into a new tunnel it would build beneath the lakebed. In the alternative, Enbridge sought a declaratory ruling from the MPSC that the company already has authority from the Commission to build the replacement segment based on the MPSC’s 1953 order that first granted permission for Line 5. The 645-mile interstate pipeline spans both Michigan peninsulas to transport light crude oil and natural gas liquids, including propane used for home heating in Michigan.

In their June 30, 2020, order, the Commission found that, based on Enbridge’s application and comments received from stakeholders, the Line 5 project differs substantially from the pipeline approved in 1953, and therefore the company does not have authority for the project under the 1953 order. Whereas the Commission approved in 1953 dual 20-inch pipelines constructed on the lakebed, Enbridge proposes replacing them with a single 30-inch pipeline housed in a concrete-lined tunnel 60-250 feet beneath the lakebed, involving a new easement and a 99-year lease of public trust property.

The order states that Enbridge is required to file an Act 16 application, pursuant to Rule 447(1)(c) and Commission precedent, to obtain Commission approval to construct the Line 5 project through a contested case. The Commission found that the Line 5 project involves important factual, policy and legal issues best resolved through a proceeding that includes discovery, comprehensive testimony and evidence to provide a robust record. The Commission observed that this proposal is a matter of significant public interest best addressed through a contested case.

The Commission in April put Enbridge’s application on hold while it considered the issue of a declaratory ruling and established a public comment period during which it sought public input specifically on any legal analysis of issues pertaining to Enbridge’s request for a declaratory ruling. A number of stakeholders filed comments opposing Enbridge’s request, including the Office of Attorney General Dana Nessel, more than a dozen Indian Tribes, a number of Michigan-based and national environmental organizations, and State Sen. Jeff Irwin. The Commission also received thousands of  comments from Michigan residents, both in support of and in opposition to the tunnel project, many discussing the merits of Line 5 rather than focusing on the legal issues surrounding Enbridge’s request for a declaratory ruling.**

Following the June 30 order, a notice of hearing will be issued with information on the scheduling of a prehearing conference and deadline for parties seeking to intervene in the formal contested case proceeding.   

Opportunities to monitor and participate in MPSC’s Line 5 proceedings  

The MPSC is scheduling a public hearing on Aug. 24 to provide an overview of the MPSC process and Enbridge’s application and for commissioners to hear directly from the public. The hearing will be held remotely with telephone and web access options. Additional details will be provided in the coming weeks. 

The MPSC launched a dedicated webpage, www.michigan.gov/MPSCLine5, to enable the public to monitor Enbridge’s siting application and related requests. Background resources on the MPSC’s siting authority under Act 16 and opportunities for the public to participate are available.  Individuals can sign up for e-mail updates on MPSC meeting notices, orders, press releases, public meetings, or other developments specifically related to the Line 5 proceeding before the Commission.  Instructions are also available for individuals seeking to sign up to be notified of all formal case filings through the MPSC’s e-dockets system. Additional information will be posted on the website as it becomes available.

To watch recordings of the MPSC’s meetings, including the June 30, 2020 meeting, click here.

To view the MPSC's June 30 order, click here.

For information about the MPSC, visit www.Michigan.gov/MPSC, sign up for one of its listservs, or follow the Commission on Twitter.

Editor's Notes:

* ex parte = from or on one side only of a dispute, as a divorce suit; without notice to or the presence of the other party. (From dictionary.com)

** See our May 8, 2020, article, "Michigan Public Service Commission seeks public comment on Enbridge Line 5 - tunnel request by May 13."