See our right-hand column for announcements and news briefs. Scroll down the right-hand column to access the Archives -- links to articles posted in the main column since 2007. See details about our site, including a way to comment, in the yellow text above the Archives.
Showing posts with label water treatment. Show all posts
Showing posts with label water treatment. Show all posts

Saturday, August 18, 2012

Letter: Comments on Keweenaw Now's Aug. 4 article, "Keweenaw Now tours Rio Tinto Eagle Mine water treatment plant"

[Editor's Note: Jack Parker, mining engineer, whom we quoted in our Aug. 4, 2012, article, "Keweenaw Now tours Rio Tinto Eagle Mine water treatment plant," recently sent the following comments on this article. We are printing them here as a letter to the editor.]

Dear Editor:

No comments to date, August 16th -- so somebody had better do it. I will.

It should be recognized that the water-treatment plant is Kennecott’s showpiece, and they have put a lot of work and money into it to show us how much they want to save Lake Superior from pollution. Give them five points for that but realize that they do not know how much water they will have to treat, how much will come from the mine and how much Mother Nature will send as rain and snow and floods, or what will be in the water.  Neither do they know where the treated water will go.

To get a fix on mine water they did test the permeability of the rock, as you were told, and found it to be low; but any thinking person would suspect that greater quantities could come from broken rock and fissures, not through intact rock. The diamond drill cores show plenty of both, and, contrary to standard practice, driller reports of water encountered or water lost were not in the application for permits.

Similarly we are told that the treated water will infiltrate the soil at the drainfield and flow gradually to the northeast. An impervious layer "C" of clay and silt "will" keep that water in the upper aquifer and prevent it going downward into the lower aquifer, maybe into bedrock above the mine, maybe back into the mine.

What they did not tell you, and perhaps nobody told your guides, is that there are big holes in that "impervious layer." One of them is at the infiltration site. When they presented their study to MDEQ (Michigan Department of Environmental Quality) for approval they "forgot" to include those test borings which showed the gaps. For their study they spaced their test holes hundreds or thousands of feet apart, which is entirely inadequate in the highly variable glacial geology at the site. Their interpretation of the data from those holes is, therefore, questionable, as a hasty effort which a freshman geology student might submit. (See the "North Jackson Hydrogeological Report."**)

But note that MDEQ did not object to or reject the report. That should raise your eyebrows.

Note that the mine will be under or near one of the several branches of the Salmon Trout River, not under the main stream.

The surface plant is impressive, exceptionally neat. Good housekeeping.

The tunnel is not being "drilled," as if by a boring machine, but drilled and blasted conventionally.

Most of the water they treat today comes from precipitation. That may not be the case if and when the mine goes into production. Neither should we expect to be able to predict amount of precipitation. Ask NOAA about 100-year floods.

The statement that the effluent from the plant will be sampled monthly should have been questioned. Would the 5 minutes of sampling be representative of the one month of operation, which is 43,200 minutes? No way! And a schoolboy would quickly learn that there are good times to take samples and times to be avoided. "Selective sampling" we call it. But MDEQ raises no objection.

In answer to Steve Garske’s question about possible lowering of the water table your guide told you about the "impermeable" layer preventing interaction of mine water and ground water, without considering the holes in layer "C." She even pointed out that there are other test wells, sampled quarterly, but that won’t help.

Then Dan brought the conversation back to the treatment plant.

I, JP,  don’t know enough about water treatment to comment on the process but believe that since they frequently promise water "too pure to drink" they will have to keep that promise.

Dan’s statement that "A coagulant creates bigger chunks so it settles solid metals" may or may not have been misquoted. The coagulant causes fine particles to clump together so that they are more easily settled and/or filtered. Metals may or may not be involved.

I am curious about the large amount of solids filtered out, shown in a bin. Are they mostly vegetable material, blown into the water?

What chemical contents might not be acceptable to the County Landfill?

I remember the sodium zeolite ion exchange. One of my jobs as a kid was to replenish the sodium chloride every weekend, at home. After refilling we had to flush the system, down the drain.

At the reverse osmosis stop I would have asked how much electrical power is needed at full capacity. I know that it’s a lot, but wonder if that’s really why they switched from diesel gens to line power.

I would not dwell on the HCl spill too much. For them it was a welcome, easily-handled diversion.

Most important, I think, is the fact that "accidents" do happen. If an accident is defined as a happening which could not have been prevented -- then most accidents are not really accidents. My truck will never run into anybody if nobody drives it. If a mine collapse could have been prevented it will not be an accident.

"The treated water will be sampled." Here again I think that sampling should be continuous, not subject to deceptive selection. An example of selectivity: At the White Pine smelter rubber-coated copper cables generated thick black smoke -- so woe betide the operator who dumped some in the furnace on day shift!

Next we head for the underworld. "Development rock … does not contain nickel and copper ore." That is not necessarily true. Some of it will.

"All development rock will be returned underground as fill." Given the changes in ventilation system -- (Did anybody see an amendment for that, or participate in public comment?) -- that rock will have to be trucked in via the portal, right?

"Every 100 ft the tunnel drops 13 feet." A giant staircase. Hard on trucks and kidneys.

The close-up photo of the portal shows a vent pipe going into the tunnel structure. Will the air there be recycled? We’ll see, when we get some frosty mornings and condensation.

"The tunnel is to be a mile long." That does not include the spiral ramp down to the sump, does it?

Neither does it prepare for production, right?

Maybe I’m wrong, but I thought that the area at Eagle Rock inside the outer fence "was not to be disturbed." It has been disturbed significantly. For example -- there is now an inner fence -- an open admission that the application statement that there was nothing of religious or historical interest was a false statement.

I see mention of "Partially treated waste water?" Is that correct?

There are quotes from my earlier trip report, and that’s OK. Missing is the most significant statement, I think, which is that I thought that the men on the job were earnestly striving to do good work and should be exonerated from all blame -- but that MDEQ and upper KEMC/Rio Tinto management should be prosecuted for submitting/accepting a substandard, deceptive and fraudulent application and a questionable mine plan. That has not changed.

Jack Parker, Mining Engineer
Toivola, Michigan

P.S. Surely there is something amiss about Dan's statement that Kennecott Exploration "Has found no mineralization."  Please explain ...  jp

Notes:

* Click here to read our Aug, 4, 2012, article, "Keweenaw Now tours Rio Tinto Eagle Mine water treatment plant."

** Click here for this this April 24, 2005, report: "Kennecott Minerals Company Eagle Project Environmental Baseline Study Bedrock Hydrogeologic Investigation, prepared by Golder Associates Ltd.

Saturday, August 04, 2012

Updated: Keweenaw Now tours Rio Tinto Eagle Mine water treatment plant

By Michele Bourdieu

Kristen Mariuzza, right, Rio Tinto Eagle Project environmental and permitting manager for technology and innovation, and Dan Blondeau, center, Rio Tinto advisor in communications and media relations, field questions from Steve Garske of Marenisco, Mich., as they explain steps in the water treatment system of the Eagle Mine. In the background is the  Degassifier, used to remove carbon dioxide from the water being treated. (Photos by Keweenaw Now unless otherwise indicated.)

HANCOCK -- About a year ago, Keweenaw Now reported on Rio Tinto-Kennecott's public forum in Marquette, during which their representatives introduced the company's new water treatment facility for the Eagle Mine near Big Bay, where they plan to mine for copper and nickel in an ore body under the Salmon Trout River. At that forum concerned citizens expressed many concerns about the water and how the company planned to prevent acid mine drainage from contaminating the rivers and streams of the Yellow Dog Plains -- and ultimately Lake Superior. Some questions were answered, some not.*

Thus, when Dan Blondeau, advisor in communications and media relations for Rio Tinto, recently invited Keweenaw Now to take a tour of the Eagle Mine, now that the water treatment facility is in operation as the mine tunnel is being constructed, I decided this would be a good opportunity to learn how it works and to what extent it protects the water. Botanist Steve Garske of Marenisco, Mich., accompanied me on this private tour on July 16, 2012. We both asked questions of Blondeau and Kristen Mariuzza, Eagle Project environmental and permitting manager for technology and innovation, who is also a Michigan Tech University graduate in environmental engineering.

The tour began outside the plant within view of the two large contact basins, together holding 11.5 million gallons of water.

This photo shows parts of the two contact basins and the paved contact area from which they collect water to be treated in the plant. In the background is the portal to the mine, through a decline tunnel being drilled under Eagle Rock, the tree-covered outcrop at the left.

"All of the water from the contact area  will flow into these basins, and then all that water is treated through our water treatment plant," Mariuzza said. "Anything that leaves the contact area has to get washed before it leaves. So equipment that operates underground can drive on the contact area, but before it leaves the paved contact area it has to be washed through our truck wash. Water from the truck wash goes into the contact basins."

Mariuzza said the majority of the water they treat is storm water. The basins collect snow melt, any rain that falls on the site, water from the underground and water from the rock storage pad. Effluent from the water treatment plant is sampled monthly, she explained. This depends on how often the company is running the plant.

Garske asked Mariuzza whether dewatering the mine would lower the water table and the Salmon Trout River, because the water table reaches the surface in the river and the wetlands around the river.

View of the Salmon Trout River. Rio Tinto-Kennecott is drilling toward an ore body of copper and nickel located under this trout stream. (Keweenaw Now file photo)

Mariuzza said there are two separate (unconnected) aquifers with a confining layer in between them.

"Seepage into the mine is not expected to have any effect on the overlying water resources," Mariuzza said. "The bedrock in the area of the underground mine workings has a very low permeability; therefore it is not a direct channel to the overlying aquifers and wetlands." 

Blondeau noted the contact area at the mine site is sloped so that all water in the contact area flows to the contact basins.

"The 'non-contact' water basins are located outside of the contact area," he added. "Therefore, they do not come into contact with mining related activities. They collect storm water (rain and snow) at three locations within the mine site."

Water will flow to these non-contact basins and be naturally reabsorbed into the ground.**

To a question on the test wells, Mariuzza replied they are all permit required wells. The groundwater wells are sampled quarterly.

"We even have wells off-site that we sample," Mariuzza added.

Blondeau described the water treatment plant as "the heart of the site."

"The whole site is designed to treat water," he said.

Inside the plant, Blondeau and Mariuzza showed us each step in the water treatment process.

First, when the mine wastewater comes into the plant to be treated, if petroleum has been detected in the water before it reaches the water treatment plant, it goes through a Nutshell Filter, which is actually made of crushed nut shells. This removes oil from the wastewater.

Next is the Degassifier, which is used to remove carbon dioxide from the water being treated (photo above). The process is similar to the way carbon dioxide escapes from a bottle of soda when you open it.

A breakpoint chlorinator removes ammonia from the water only when the ammonia is high.

The Multiflo Clarifier  removes scale-forming constituents such as calcium and magnesium from the water.

The Multiflo Clarifier removes such constituents as calcium and magnesium from the mine water.

"Basically it slows down the water flowing through the plant," Blondeau explained.

He said a coagulant creates bigger chunks so it settles solid metals.

The clean water, from the tank pictured here in the background, goes to the Multi Media Filters, and the waste stream (in the tank in the foreground), goes to the Filter Press.

Next, the solids filtered out of the water are tested and the results are sent to a landfill.

This area is referred to as the 'Filter Cake Disposal' bin. The material is tested, results are given to the Marquette County Landfill (MCLF), and the MCLF determines if the contents can be placed in the landfill. If the contents do not meet the requirements of the MCLF the contents are sent to a facility that accepts the material.

"The MCLF (Marquette County Landfill) has already accepted material from our operations," Blondeau said. "If they decide not to accept them, the test results are sent to a facility that will accept the material. Should they be considered hazardous waste, they would have to be sent farther away (possibly to Detroit or Wisconsin) to a hazardous waste facility."

Mariuzza added, "We don't expect that this will ever come up as a hazardous waste product."

Once the larger solids are removed, multimedia filters (made of different materials) help remove any suspended solids that haven't settled yet, Blondeau explained.

The next step is the Sodium Zeolite Ion Exchange, which removes hardness from the mine water.

This photo shows the Sodium Zeolite Ion Exchange filters. Only two are ever operating at one time. The third unit is on standby; for example, in the event of maintenance the system continues to operate. (Photo © and courtesy Rio Tinto)

In his right hand, Blondeau is holding the contents of a Multi Media Filter and in his left he is holding the contents of the Sodium Zeolite Ion Exchange filter. These contents are placed in the clear containers so that people can see what is inside each filter. The Multimedia filters help remove suspended solids from the water similar to the way a coffee filter removes coffee grounds. The Sodium Zeolite filters remove hardness from the water similar to household water softeners.

Finally, the Reverse Osmosis process (RO) helps purify and treat the water so that it can be reused and recycled. It is similar to the technology used in bottled water.

"We go through the reverse osmosis process two times," Mariuzza said.

This Reverse Osmosis system removes ions from water that has already gone through the previous steps. (Photo © and courtesy Rio Tinto)

"The less you have to pull through these filters the better," she noted. "It's like a screen, but the mesh is so small it removes ions. You can't even see the holes in the filter."

A pump pushes water through the small holes creating pressure -- 500 pounds per square inch (psi) on the first pass and 200 psi on the second, Mariuzza explained.

"Our product water is what gets discharged," she said.

Reverse osmosis also removes mercury present in rainwater in order to meet standards. The pH of the product water is close to neutral. If for any reason it is above or below the standard, the water is taken through the whole process again, Mariuzza added.

Because of a recent spill of hydrochloric acid at the plant, we asked what it was used for.

"One of the things we use hydrochloric acid for is to adjust the pH," Mariuzza said.

Both Blondeau and Mariuzza confirmed the acid spill was in a contained area and under control.

The Yellowdog Watershed Preserve (YDWP), on their Web site, expressed concern about the spill even though the company said they were not overly concerned about potential environmental damage.

"While the mining company considered this a 'relatively small' spill, hydrochloric acid is a strong, highly corrosive acid which can be very harmful to human tissue," the YDWP article stated. "YDWP will continue to keep an eye on the situation and be a leading force in monitoring our local resources to ensure our community is protected."

Following the Reverse Osmosis, an evaporator is used to remove the liquid fraction from the liquid waste, and the water vapor is condensed and mixed back into the treated reverse osmosis water. The Crystallizer removes salts that are tested and sent to a landfill that accepts waste.

In this photo the Evaporator is on the right and the Crystallizer is center/left of the two white pipes.

Mariuzza said the product water is sampled before it goes to the discharge -- a Treated Water Infiltration System (TWIS). The process is similar to a drainfield. It goes through perforated pipes into the groundwater, and test wells sample it.

Next we rode in the Rio Tinto vehicle to see the Temporary Development Rock Storage Area. Development rock is waste rock from the decline tunnel and does not contain nickel and copper ore.

This storage facility is for development rock, which is all rock removed from the underground that is not considered ore. The facility features a multi-layered liner, leak detection system and sump pump to collect water which will be treated by the water treatment plant. It is considered environmentally secure. All development rock will be returned underground as fill.

We asked if we could ride closer to the portal for a photo of the decline tunnel now being drilled under the outcrop known as Eagle Rock in order to access the ore body.

The decline tunnel is 18 feet in diameter and descends under Eagle Rock at a 13 percent grade (Every 100 feet it drops 13 feet).

This closer view of the decline tunnel shows the orange part of a pipe going underground and pulling clean air into the tunnel. (Photo © and courtesy Steve Garske)

According to a recent L'Anse Sentinel article about a July 25, 2012, Rio Tinto community forum in L'Anse, the company said the tunnel is to be a mile long and is now 70 per cent complete.

Local residents seek air quality monitoring

Big Bay residents recently complained about diesel fumes and a filter being removed from the exhaust of the tunnel. They are seeking an independent air monitoring program for the region. Carla Champagne of Concerned Citizens of Big Bay expressed these concerns at Rio Tinto's Annual General Meeting (AGM) in London, England, last April. In May,  Powell Township passed a resolution stating, "in response to Citizen’s concerns, we the Powell Township Board do ask that the Environmental Protection Agency and or the Michigan Department of Environmental Quality develop an Air Quality Monitoring program in our region, with monitors installed at present and future mine sites, within the community of Big Bay, and at any other sites in Powell Township that these agencies deem appropriate."***

Both Mariuzza and Blondeau said they have never smelled diesel in the tunnel.

"We have refined the design of the mine, and we have identified measures and systems that can reduce overall air emission impacts from the site," Blondeau said. "MDEQ
(Michigan Department of Environmental Quality) requires a new permit application to be filed if there is a change in quality, nature or quantity impact of emissions. In accordance, we filed the new air permit in March of this year. The revised permit does not include a baghouse filtering system. A baghouse would not work properly because expected emissions will be so low that the filter would not work properly. Baghouse filter manufacturers have advised us that their products are not designed for emissions as low as ours. We are working with Superior Watershed Partnership on a community monitoring program. A portion of the monitoring will directly address air."

Blondeau also commented on the fence around Eagle Rock, which the Anishinaabe (Ojibwa) people consider a sacred site.

This photo shows the outcrop, Eagle Rock, which is surrounded by a fence. The decline tunnel being blasted to access the ore body is at right. (Photo © and courtesy Steve Garske)

"Activities prohibited in our lease include, 'Clearing of, or mining operation activities on the rock outcrop,'" Blondeau noted. "We are not allowed to remove any trees or vegetation from the area inside the fence."

He said the fence is several meters out from what is defined as the rock outcrop.

"When members of the Keweenaw Bay Indian Community (KBIC) visit the rock we do not go up on the rock with them unless they invite us up," he added.

Native Americans visit Eagle Rock

Although two Native Americans were arrested when the fence went up in 2010, Native people are allowed to visit Eagle Rock for spiritual ceremonies.

Two Keweenaw Bay Indian Community (KBIC) members who visited Eagle Rock recently -- Charlotte Loonsfoot and Jessica Koski -- shared their impressions with Keweenaw Now.

"Native People are not allowed to hold our ceremonies as we desire to at Eagle Rock," Loonsfoot said. "If we were able to stay about four nights and four days, then we would be able to do our Ceremonies, but they tell us we have to leave every night which is not allowed in our way. I hope someday this may change as we really need to help our spirits heal from all the pain and turmoil Kennecott/Rio Tinto has imposed on us."

Koski said she has visited Eagle Rock twice since the fence was put up around it in 2010 -- once shortly after "the arrest of two fellow tribal members who were honorably defending our sacred place, lands and waters from the disruptive intrusion of a foreign extractive mining company on our traditional Anishinaabe lands."

Her second visit was on July 20, 2012, when she took a small group of KBIC high school students to the Yellow Dog Plains.

"We gathered lots of wild raspberries and saw traditional trail marker trees of ancestors. We visited and drank from some of the freshwater springs there that help feed the headwaters of the Salmon Trout River. It was the most clean, cool, refreshing water I have ever tasted," Koski said. "Unfortunately, these springs are hydrologically connected to an aquifer that is to be injected with at least 20,000 gallons per day of partially treated waste water from the Eagle sulfide mining project."

Koski said that for her and the students it was not a mine tour, but a visit to a sacred place.

"Imagine, you are going to Church, but before you go you have to get permission from a company who is doing heavy construction all around and beneath. You are not sure whether it is a completely safe place to visit as you can smell chemicals and explosives lingering in the air, but it is your Church where your family has gone for many generations, so you can't just move to a new Church. Then image that you are escorted to a guard office, read liability legal language, and asked to put on a corporate hard hat, safety goggles and florescent vest. Then, you are not free to proceed on your own to your Church. A company official, or two, have to walk you to your Church. Then, as you finally reach the Church, the company official 'allows' you to go in, but stands and observes nearby. Just as you are about to proceed, you hear and feel blasting and rumbles beneath your feet." ****

Mine tour impresses; concerns about water remain

Garske said he found our tour interesting and the guides effective in doing their job.

"My overall impression of the tour was that our guides were intent on convincing us that everything was going well and according to plan, that the company was doing everything they can to see that the water would not be contaminated, that the rock would be protected, and that everything would be just fine," Garske said. "That's their job and they were working fairly hard at it."

However, he added he still has some concerns about the water and the Salmon Trout River.

"From what I've seen and heard, the hydrology of this whole area is extremely complex," Garske said.

He said he was also wondering how the company could keep water from the river from percolating (or gushing, if the mine collapses) into the mine, thus lowering the water table and the river.

"I am also concerned (as many others have been from day one) about potential leaching of acid and metals from the mine," Garske added. "Can this leachate be prevented from entering the groundwater and eventually making its way underground, north to the springs and streams that flow into Lake Superior?"

Mining expert Jack Parker, who has expressed concern about a possible collapse of the mine based on the plans in Kennecott's mining permit application, toured the mine in October 2011 with Michigan Tech professor Stanley Vitton, shortly after the blasting in the portal began. While Parker did not tour the water treatment plant, his overall impression was that Rio Tinto-Kennecott was trying to do everything right.

"My unanswered questions are related more to the application -- are the data in the mine design and planning the only departures from reality?" Parker writes. "So in Water Treatment I truly question the projected water quantities and chemistry. RT (Rio Tinto) is relying on figures in the application. Nobody here on Earth can vouch for future climate.   I wonder how often we will experience 100-year floods …"

Parker commented favorably on the mining equipment he saw.

"We saw the mining equipment -- all first-class," Parker notes. "An electric/hydraulic face-drilling jumbo, computer controlled, costs $1,250,000, as did the backup machine.  The underground haulage trucks carry 50 tons. Highway trucks will actually carry 50 tons in two 'bins' on two trailers, with one prime mover."

These are the mine haulage vehicles that go underground.

Parker also entered the decline tunnel and was impressed by the safety features and precautions.

After mine closure, Blondeau said, the water treatment plant must remain on the site at least five years as part of the 20-year post-closure monitoring.

"If for some reason we still need it after five years, we would leave it up," he said. "After closure everything has to be taken out (buildings, concrete, etc.)."

The mine will be backfilled as they drill upwards. Primary stopes will be backfilled with cemented rock, and secondary stopes will be backfilled without cement, Blondeau explained.

"It's really a very small, concentrated ore body," Blondeau said.

Although the original application said the ore would be hauled to a railhead near Marquette, it is now to be hauled to a mill at Humboldt.

"The DEQ doesn't have jurisdiction on the route," Blondeau explained. "Our permit doesn't specify the route we have to take." *****

The Eagle Mine project now employs more than 60 percent local employees, Blondeau said. At the time of this tour the total number was 90 employees of whom 61 were local.

"Again, this includes Kristen and me," he added. "I was born and raised here. I have the utmost confidence in our people (RT). ... If I didn't think they were doing everything right I wouldn't work here."

Mariuzza, also a local resident, said she worked for the Michigan DEQ for 10 years, then took three years off to stay home with her young children before accepting the position with Rio Tinto.

"I think we have a great environmental program and monitoring program," she said.

Keweenaw Now asked Blondeau about Rio Tinto's current exploration activities at various sites in the region.

"We continue to explore the central and western UP, but we haven't found any mineralization yet," Blondeau replied.

NOTES:

* See our May 3, 2011, article, "Updated: Residents concerned about water quality question Rio Tinto-Kennecott at community forum."

** See Rio Tinto's Web site for overview photos and a site legend.

*** See our May 23, 2012, article, "Updated: Big Bay residents report on Rio Tinto AGM in London."

**** Jessica Koski recently posted these comments on Facebook. UPDATE: Click here to read Koski's complete article, "Political Ecology in the Upper Peninsula of Michigan: A Sacred Place or Mine Portal?" posted Aug. 8, 2012, on Stand for the Land.

***** Rio Tinto is presently considering the proposed County Road 595 as a haul route to the mill at Humboldt, but federal agencies have concerns about potential environmental impacts if this road is built. The Michigan Department of Environmental Quality is considering issuing a wetlands fill permit to the Marquette County Road Commission under Section 404 of the Clean Water Act and Sections 301 and 303 of the Michigan Natural Resources and Environmental Protection Act for the proposed County Road 595. According to MCRC's permit application, construction would affect 25.81 acres of wetlands and require building 22 stream crossings. The Environmental Protection Agency has raised concerns about the wetland and stream impacts and will hold an informational public meeting at 6 p.m. followed by a formal public hearing at 7 p.m. on Tuesday, Aug. 28, at Northern Michigan University's Don H. Bottum University Center Ontario/Michigan/Huron Rooms, 1401 Presque Isle Ave., Marquette. Click here for details.

Tuesday, May 03, 2011

Updated: Residents concerned about water quality question Rio Tinto-Kennecott at community forum

Matt Johnson, Kennecott manager of external affairs, begins his presentation on the Rio Tinto-Kennecott Eagle Mine during Kennecott's April 26, 2011, community forum at the Ramada Inn in Marquette. (Photos courtesy Allan Baker.)

By Michele Bourdieu

MARQUETTE -- More than 150 people filled a large room at the Ramada Inn in Marquette on April 26, 2011, for the fourth in a recent series of community forums hosted by Rio Tinto's Kennecott Eagle Minerals Company (KEMC) for open discussion of the Rio Tinto-Kennecott Eagle Mine on the Yellow Dog Plains near Big Bay, Mich.

KEMC began construction of infrastructure for the mine about a year ago. It is also a year since a group of Native and non-Native opponents of the mine camped out at Eagle Rock, an Ojibwa (Anishinaabe) sacred site, chosen by KEMC to be the portal for this nickel and copper mine estimated to earn the company $4.7 billion in profits.

Matt Johnson, KEMC manager of external affairs, assisted by Chantae Lessard, KEMC senior advisor for government and community relations, gave a 20-minute Power Point presentation on the project and then opened the forum to questions and discussion. The majority of those in the audience who asked questions or presented their views appeared to be concerned citizens opposed to the Eagle Mine, but some declared themselves to be neutral on the issue or in favor of the mine and KEMC.

Frank Jeff Verito, a 19-year Marquette resident, formerly from Wisconsin, said he came to the forum to hear what Kennecott had to say and to have the opportunity to make a public comment.

During the April 26 community forum, Frank Jeff Verito of Marquette expresses his views on the impacts of Kennecott's Eagle Mine.

"I moved here because it was one of the least spoiled places, and now it’s being spoiled," Verito said.

During the forum, Verito read a statement with his opinions, saying, "We’ve seen Kennecott demonstrate the epitome of the step-by-step, hurdle-by-hurdle approach that corporations use to cram their filth down the throats of residents who want no part of them. First they influenced the DEQ to grant their application, which some of us knew was a done deal from day one. Then suddenly an untold number of trees were destroyed for power lines, followed by the urgent need for a haul road, which would consume more acreage than the mine site itself, not to mention the wetlands, the moose habitat, and access for major future developments over some of the UP’s wildest remaining areas."

Verito said he had spoken with residents of Ladysmith, Wis., site of Kennecott’s Flambeau Mine, (now the subject of a lawsuit over water pollution from that mine). He said he believed there is no safe way to do sulfide mining near a fragile aquifer.

Potential water pollution was a major concern in many of the comments made at this forum.

Johnson, apparently aware of this concern, emphasized the importance of the water treatment facility now being built at the Eagle Mine. During the presentation, Johnson projected a slide with an aerial photo, taken last fall, of the 100-acre site, noting the site has been designed to have water management as a priority. He explains this in the following video clip:



Using an aerial view of the Eagle Mine site on dual screens, Matt Johnson, Kennecott manager of external affairs, with the assistance of Chantae Lessard, Kennecott senior advisor for government and community relations, points out locations where water will be treated and stored during mining operations. (Video clips courtesy Allan Baker)

Johnson noted 75 employees worked this winter on construction of the reverse osmosis water treatment facility, which the company hopes to complete later this year.

A slide in the Rio Tinto presentation states, "Our water treatment facility is at the heart of our commitment to protect water."

Lessard points one of six water tanks inside the reverse osmosis water treatment plant, still under construction. Each holds about 22,000 gallons of water.

Jennifer Silverston, a concerned Marquette resident, asked three technical questions related to Johnson’s presentation on the mining operation. First, she wanted to know how the rock (containing sulfides) removed from the mine and stored on site on a pad or liner would be prevented from reacting with air and water (which can cause Acid Rock Drainage or ARD, aka Acid Mine Drainage) before it goes back into the mine.* Second, she asked where the minerals from the reverse osmosis treatment plant would be deposited when separated from the water. Third, she asked if the company was planning for "a hundred-year storm or a thousand-year storm" with their design.

Kristen Mariuzza of KEMC, answered Silverston’s first question by explaining the rock would be stored on several liners and a leak-detection sump and would be covered as much as possible. As for the question on the minerals filtered out by the reverse osmosis system, Mariuzza said they would be "squeezed" out of the water and tested to determine whether they should go into a hazardous waste site or a regular landfill. She also explained that the company had evaluated both a 100-year rainfall event and a 50-year combined snow melt and rainfall event and decided on the latter for the design, since the combined snow melt and rainfall produced more water.

Silverston appeared dubious about the 50-year design because of climate change:



KEMC's Kristen Mariuzza replies to questions from Marquette resident Jennifer Silverston concerning the reverse osmosis system of the water treatment plant and the long-term planning for water protection at the Eagle Mine site.

Richard Sloat of Iron County said Kennecott's water treatment plant will operate at the Eagle Mine without having been tested. He asked Johnson if Kennecott would sign a letter of agreement to test the reverse osmosis plant with polluted water from the Buck Mine, an abandoned iron mine in Iron County that was located in a highly concentrated sulfide body.

Sloat questioned an explanation he received when he spoke with Rick Thomas, Rio Tinto managing director, Project Delivery Hub (Americas) Technology and Innovation.

He said Thomas told him if the treatment plant doesn't work, "we'll just tweak it later."



Richard Sloat, Iron County resident, brings up the fact that Rio Tinto - Kennecott's reverse osmosis plant, being built on the Eagle Mine site, will not have been tested before mining operations begin. He asks that Rio Tinto test it, in advance of mining operations, with polluted water from an abandoned mine in Iron County.

"I don't think that's unreasonable -- to protect our water," Sloat said. "You basically said, in a video I watched, 'We're all concerned about the water.'"

Mariuzza replied to Sloat that the water treatment plant would have to be tested with comparable water and she wasn't sure the water from the Buck Mine would be comparable. While she could not commit to such testing right away, Mariuzza admitted Sloat had good points and she did not dismiss his request.

"I won't leave this unanswered," she said.

Cynthia Pryor of the Yellow Dog Watershed Preserve expressed concern about Johnson’s description of where the tunnel would go from its entrance at Eagle Rock. He described it on the aerial photo, saying, "We actually have two plans -- one that curves around to the north, one that curves around to the south …"



Cynthia Pryor of the Yellow Dog Watershed Preserve asks for clarification on the proposed direction of the Eagle Mine tunnel.

Pryor challenged the idea of the tunnel going south because of the location of the Salmon Trout River to the south and her understanding that the permit and Environmental Impact Assessment (EIA) are based on a plan to have the tunnel going north.

Johnson confirmed the permit does say the tunnel is going to go north, but the south route was being considered:


Matt Johnson tries to answer Cynthia Pryor's concerns about potential harm to the Salmon Trout River if the Eagle Mine tunnel should be directed to the south.

Johnson then mentioned "many permit amendment approvals" by the DEQ, but Pryor noted the importance of the impact to the watershed if the tunnel were to go south.

A member of the audience asked a question about seepage into the aquifer from the broken rock in the mine.

"The water on the surface that’s supplying the Salmon Trout River -- that’s separate from the water in the underground mine," Mariuzza said.

In addition, the company will be monitoring the water level throughout the life of the mine, she added.

Barbara Bradley of Skandia spoke about the water pollution at Kennecott’s Flambeau Mine in Ladysmith, Wis.; water violations by a Kennecott mine in Alaska and both water and air pollution at their Bingham Canyon mine in Utah.

Barbara Bradley of Skandia reminds Rio Tinto-Kennecott of their past practices that violate both the Clean Water Act and the Clean Air Act.

Johnson claimed Kennecott had worked with the EPA to clean up waste from previous mining at the Utah site in order to prevent it from being a Superfund site. As for the polluted drinking water, he noted Kennecott was providing drinking water to residents there.

Some members of WAVE (Water Action Vital Earth), a new grassroots citizens' group in Marquette, also spoke about water concerns.

WAVE member Laura Nagle of Marquette expressed concern about water from the mine that may go into neighboring wells. She also explained WAVE's purpose.

"(WAVE's) focus is to protect our clean water and create sustainable jobs within our community," Nagle said. "If we find an alternative route, then we and our grandchildren and our children will be able to live without toxins."

Another WAVE member, Margaret Comfort, spoke of toxins she was exposed to when living in the Saginaw area.

"We need to tread softly and carefully and not try to bypass things," Comfort said, "because once the water's messed up it's messed up forever."

Jeffery Loman, deputy director of the Bureau of Ocean Energy Management Regulation and Enforcement and a member of the Keweenaw Bay Indian Community, who now lives in Alaska, asked several questions dealing with trust and ethics.

He first pointed out that at both the Humboldt community forum, held by Kennecott on April 19, and at this one, Rio Tinto-Kennecott's presentations stated the legal challenges to the Eagle Mine were over. Loman asked Johnson if that is their position -- that there are no more legal challenges to their permits or projected activities for the Eagle Mine.

"There was a contested case on the Part 632 mine permits that were granted, and the judge ruled in favor of the state and the mining company’s position," Johnson replied, "and the National Wildlife Federation and others have filed an appeal on that and that’s coming up."**

Loman said he plans to ask the Administrator of EPA, Lisa Jackson -- as a matter of policy -- to designate the Yellow Dog Watershed an Area of Aquatic Resource of National Interest.

After noting Rio Tinto’s arrogance and lack of ethics in hiring state employees formerly involved with regulating their project to work on the project for them, Loman suggested a way the company could redeem itself:***



Alaska resident and Keweenaw Bay Indian Community member Jeffery Loman, deputy director of the Bureau of Ocean Energy Management Regulation and Enforcement, suggests that Rio-Tinto-Kennecott do a Health Impact Assessment (HIA) for the Eagle Mine.

To Loman’s request that Rio Tinto-Kennecott do a Health Impact Assessment (HIA), Johnson replied, "Yes, we would consider that."

Johnson noted United Nations core values the company holds are listed on their Web site.

These are listed under the principles of human rights, labor standards, environment, and anti-corruption.****

After the forum, Cynthia Pryor of the Yellow Dog Watershed Preserve summed up the reason many mine opponents attended the forum.

"Why we all came here was to bring all these issues to the public’s attention so they get a well-balanced view -- not just the company’s opinions," Pryor said.

Editor’s Notes: This is the first in a series of articles on Kennecott’s three-hour community forum held in Marquette April 26. Watch for the next article with more public comments and concerns expressed at the meeting.

*KEMC’s Web site, under "Water Protection," calls this "development rock." It says, "Development rock -- non-ore bearing rock drawn from underground as the mine is built -- contains sulphide bearing minerals. Development rock needs to be stored on the surface during the project’s construction and development, before being used as backfill. As the development period may last several years, there is a risk that ARD may occur." Click here for Kennecott’s explanation of their planned protection against ARD (Acid Rock Drainage).

** Loman noted correctly that the appeal was not mentioned in Kennecott’s presentation on the mine. The hearing on this appeal is scheduled for June 9, 2011.

*** Matt Johnson formerly worked for former US Rep. Bart Stupak and for former Michigan Governor Jennifer Granholm, although not in a regulating capacity. Kristen Mariuzza is a former DEQ employee. A note under the Jan. 28, 2011, YouTube TV-6 video interview with Mariuzza at Kennecott’s water treatment plant, under construction, states, "Mariuzza reviewed and signed off on Rio Tinto's wastewater treatment plans while with the DEQ and shortly after went to work for the company."
Click here for the YouTube video clip, "TV6 Interviews DEQ Employee-Turned Rio Tinto Employee."

**** Click here to read about Rio Tinto’s participation in the United Nations Global Compact.

UPDATE:  Click here for Part 2 of this series: "Kennecott Forum, Part 2: Comments on Eagle Rock, mining permit."